Ask a Question
Please provide the following information and a member of our Lucas School District team will be in touch with you shortly.
In keeping with Lucas Local School District’s mission statement to provide high quality educational opportunities that promote academic preparedness and productive citizenship, the Board of Education has been exploring long-term options for the district’s long-term facility needs.
The Lucas School District currently has three buildings. The elementary school was originally built in 1956. An addition was built onto it in 1963, which brought the school’s total square footage to 26,851. The middle school is the newest building in our district. It was built in 1979 and has 29,811 square feet.
The high school is our oldest building in the district. It was originally constructed in 1918 and has had two additions to increase its space and functionality during its history, the first in 1938 and the second in 1958. As the largest building in our district, the high school has 43,828 square feet.
Given the age of the three district buildings, the board has long been aware of and committed to finding a financially viable solution for our community to update our educational facilities.
An earlier assessment by the Ohio Facilities Construction Commission (OFCC) in 2005 placed Lucas School District in the “Exceptional Needs Program.” The program made the district eligible for funding toward the construction of a new PK-12 building to house 565 students and the abatement and demolition of the existing buildings. At the time, the project was estimated to cost a total of $23.7 million, with $15.6 million placed on the local ballot.
Although that project did not go on the 2005 ballot, Lucas remains a highly prioritized district for funding. In 2018, the board hired Garmann Miller to provide an assessment of the current facilities and define a capital improvements plan. A team of architects and engineers reviewed 23 assessment points that included HVAC, roofs, and electrical components of the three buildings.
When the assessment was completed in 2018, the results determined that the combined long-term and short-term costs to the district to maintain the current facilities would amount to $25.4 million. Adjusted for inflation, the total maintenance costs total $31 million today.
Before proceeding with facilities maintenance objectives, the board instead formed a facilities task force in 2019 to evaluate building renovations versus replacement to determine the best use of taxpayer dollars.
The board conducted a property survey and review of alternative options. One alternative proposed adding a high school to the renovated middle school ($19.7 million) and renovating the existing elementary school ($7.4 million), for a combined cost of $27.1 million. The new 8-12 building would add 46,000 square feet to the middle school property.
The board reconnected with the OFCC to open conversation again about constructing a new facility to house the full population of our district. Since 2005, the student population has shifted. The proposed new building master plan accommodates 474 students in 91,083 square feet. The total cost of this project is $34,185,516. The state’s share of this project is $8,067,340, which brings the local cost of the project to $26,118,176, the lowest of the three potential solutions.
As the most financially viable solution, the new PK-12 building would feature 23 academic classrooms, a 10,000 square foot competitive gym, a life skills lab, an ag-ed lab, two art rooms, an industrial tech classroom, an instrumental music room, and a business/computer lab.
Learn more and stay up to date with the Lucas Local School District’s new facilities project and other news.